Vallibel Erathna SHPP

Project Information
Country: Sri Lanka Location: Kuruwita, Ratnapura district
Technology: Small Hydro Development stage: Financial Closure
Status: Operational Number of system(s): 1
Captive facility: No Percentage captive: ..
Contract Information
Type of PPI: Greenfield project Subtype of PPI: Build, own, and operate
Contract period (years): .. Termination year: ..
Main revenue source(s): PPA/WPA payments Contract award method: ..
Bid criteria: Not Applicable Number of bids: ..
Renewal contract award method: Not Applicable Renewal bid criteria: Not Applicable
Government granting contract: State/Provincial Renewal number of bids: ..
Financial Information
Project company: Vallibel Power Erathna Limited (VPEL)
Publicly traded: No Stock market: N/A
Type of government support: ..
PPP project: Yes Related infrastructure by government:
PPP part of public project: No Key features of guarantee:
Key features to support revenue/reduce cost: Total cost of public project:
PPP type: Services contracted by the government Concession period type: ..
Banks/funds involved (depth financing):
Commissioning date: 2004 Project grid: Sri Lanka
Carbon credits: No

Sponsor Details

Sponsor % Ownership Country of origin
Vallibel Holdings 80 Sri Lanka

Project Investment History (proposed investment listed for pipeline projects)

Year % private Payment commitments to the government * Investment commitments in physical assets Capacity Type Government cash subsidy commitments
2003 100 0 7 10 MW ..

Multilateral Support Details

No details available

Funding Details

No details available