Kavarna Wind Farm

Project Information
Country: Bulgaria Location: Bulgarevo, Kaliakra municipality
Technology: Wind Development stage: Financial Closure
Status: Construction Number of system(s): 1
Captive facility: No Percentage captive: ..
Contract Information
Type of PPI: Greenfield project Subtype of PPI: Build, own, and operate
Contract period (years): .. Termination year: ..
Main revenue source(s): Purchase agreements or transmission fees with public entity(ies) Contract award method: Competitive bidding
Bid criteria: Not Available Number of bids: ..
Renewal contract award method: Not Applicable Renewal bid criteria: Not Applicable
Government granting contract: Local Renewal number of bids: ..
Financial Information
Project company: EVN Enertrag Kavarna OOE
Publicly traded: No Stock market: N/A
Type of government support: ..
PPP project: Related infrastructure by government: ..
PPP part of public project: Key features of guarantee: ..
Key features to support revenue/reduce cost: .. Total cost of public project:
PPP type: .. Concession period type: ..
Banks/funds involved (depth financing):
Commissioning date: Project grid: ..
Carbon credits:

Sponsor Details

Sponsor % Ownership Country of origin
Energie Versorgung Niederosterreich (EVN) AG 70 Austria
Enertrag 30 Germany

Project Investment History (proposed investment listed for pipeline projects)

Year % private Payment commitments to the government * Investment commitments in physical assets Capacity Type Government cash subsidy commitments
2009 100 0 132 50 MW ..

Multilateral Support Details

No details available

Funding Details

No details available