Project company: |
Solar Park Bulgaria |
Publicly traded: |
No |
Stock market: |
N/A |
Type of government support: |
.. |
PPP project: |
Yes |
Related infrastructure by government: |
|
PPP part of public project: |
No |
Key features of guarantee: |
|
Key features to support revenue/reduce cost: |
20 Year PPA, EUR 248.3/MWh |
Total cost of public project: |
|
PPP type: |
Services contracted by the government |
Concession period type: |
Fixed concession Period |
Banks/funds involved (depth financing): |
Other Commercial Bank |
Commissioning date: |
2012 |
Project grid: |
Bulgaria |
Carbon credits: |
No |
Sponsor Details
Project Investment History (proposed investment listed for pipeline projects)
Year
|
% private
|
Payment commitments to the government *
|
Investment commitments in physical assets
|
Capacity
|
Type
|
Government cash subsidy commitments
|
2012
|
100
|
..
|
20
|
5
|
MW
|
..
|
Multilateral Support Details
Funding Details